The installation process of mobile gantry crane is divided into several parts, such as: structural components installation, mechanical components installation, electrical components installation, etc. Today we will introduce the electrical cable installation.
 
1. The midpoint of mobile gantry crane travel rail is the best electrical cable fixing point.
 
2. The electrical cable should have fixed bending clip to make the cable to move left and right, the detailed size can be selected by the cable specification design; shaft pin diameter can be taken 40 ~ 50mm.
 
3. Between the electrical cable and fixed bending clip should have cushion to prevent damage to the cable.
 