Gantry crane manufacturer
1. When the track joints are not welded in one case, should meet the following requirements:
a. The height difference between joints should not be greater than 1mm.
 
b. The joints gap should not be greater than 2mm gap.
 
c. The joint lateral dislocation should not be greater than 1mm.
 
d. For box girder, the track joint shall be placed on the rib plate, and the error shall not exceed 15mm.
 
e. The track longitudinal gradient should not exceed 0.5%.
 
f. The rail must be fastened by bolts and pressure plate, the gasket should not move, and the pressure plate should be fixed firmly.
 
g. The track should not have cracks or serious wear which can affect the safe operation.
 
h. During gantry crane traveling, when there is a gripping rail or track gauge S≤10m, the △ s = ± 3mm; when S> 10m, △ s = ± [3 + 0.25 (S-10)] mm, Should be not more than ± 15mm.

Single girder gantry crane Manufacturer

 
 
Gantry crane manufacturer
2. When the gantry cranes come out gripping rail, should check the span limit deviation, the inspection requirements:
a. If the gantry emd beam is detachable, and with directly loaded wheel, the gantry crane span limit deviation should be:
When S≤10m,△s=±2mm
When S>10m,△s=±[2+0.1(S-10)]mm
 
b. If the gantry cranes apply welded end beam and angular bearing box wheel, the gantry crane span limit deviation △ s = ± 5mm, each pair wheels span measured relative relative difference should not be greater than 5mm.
The driving wheel should rotate synchronized in the same direction.
 
Double girder gantry crane manufacturer